RADCOM’s second-quarter 2026 results contained a detail that matters well beyond one telecom software vendor. Revenue fell to $11.8 million from $17.7 million a year earlier, and management attributed the decline to deployment delays at customers rather than lost deals: higher component costs and supply constraints slowed the buildout of the infrastructure needed to run the software, and purchasing decisions moved with the schedule. No delayed deployment was reported as cancelled or lost to a competitor.
That is the shape of the problem across enterprise AI right now. Dell has described on-premises AI as a growth tailwind precisely because organisations want inference to sit closer to their data. The demand is real. The constraint has shifted from whether to deploy locally to when the racks, power, and network capacity are actually available — and to what a programme is supposed to do in the meantime.
The failure mode this creates is subtle. A programme that has coupled every deliverable to the arrival of the final cluster does not simply run late; it runs idle. Twelve months later, the hardware is racked and the team is only then discovering that the document repository permissions are inconsistent, that three source systems have no usable API, and that nobody has agreed who approves an automated action.
What actually slips, and what does not
It helps to separate the dependency chain honestly. Very little of an enterprise AI programme is genuinely blocked on accelerators.
| Work stream | Needs the target cluster? | Notes |
|---|---|---|
| Source-system access and connectivity | No | API contracts, service accounts, network paths, rate limits |
| Permission and entitlement mapping | No | Usually the longest-pole non-hardware task |
| Document ingestion and chunking design | No | Testable at small scale on existing servers |
| Retrieval quality evaluation sets | No | Needs subject-matter experts, not GPUs |
| Workflow and approval design | No | Who decides, who reviews, what is logged |
| Audit and evidence requirements | No | Driven by compliance, not capacity |
| Small-model pilot for one workflow | No | Runs on modest existing capacity |
| Production concurrency for many users | Yes | Throughput and tail latency depend on serving capacity |
| Large-context or large-model workloads | Yes | Memory-bound; genuinely accelerator-gated |
| Fine-tuning and continuous evaluation at scale | Yes | Batch capacity, not interactive capacity |
Read down the “No” column and the point becomes uncomfortable: the work that most often determines whether an AI programme reaches production is the work that never needed the hardware. Permission mapping in particular tends to expose years of accumulated inconsistency in shared drives, case systems, and record stores. That discovery is far cheaper during a hardware wait than after it.
Sequence the programme in four stages
The objective is a plan where each stage produces something durable, and where the arrival date of the final capacity changes when value scales, not whether the programme progresses.
Stage 0 — Evidence and access (no new hardware). Fix the scope to one or two workflows with a measurable baseline. Establish connectivity and read access to the source systems. Map entitlements to the identity model that will govern retrieval later. Write the evaluation set: real questions, real documents, expected answers, and the cases where the correct behaviour is refusal or escalation. Agree what a complete audit record must contain.
Stage 1 — Constrained pilot on existing capacity. Run one workflow end to end with a small model on hardware you already own. The point is not benchmark performance; it is to prove the pipeline — ingestion, permission-aware retrieval, generation, validation, human approval, and logging. Small language models make this stage viable far more often than teams expect, as covered in Small Language Models in Enterprise AI Infrastructure.
Stage 2 — Governed production on interim capacity. Move one workflow into real use for a bounded user group. This is where operational reality appears: queue behaviour under concurrent load, retrieval gaps, edge-case documents, approval fatigue. Interim capacity can be a single accelerated server, a repurposed cluster node, or existing CPU capacity for lighter workloads.
Stage 3 — Scale onto target capacity. When the racks land, the migration is a re-host of a working, evidenced system rather than a first deployment. Sizing is now based on measured token throughput, context distribution, and concurrency from Stage 2 rather than a vendor estimate — the input that Estimating GPU Requirements for a Local LLM depends on.
Design procurement so a delay is not a penalty
Hardware slippage becomes expensive when the commercial structure assumes a single delivery date. A few adjustments materially reduce that exposure.
- Start the licence term when the platform is usable, not at signature. A twelve-month term that begins three months before the environment exists is a straightforward loss.
- Prefer capacity-aligned terms over per-node or per-GPU counts. A phased rollout should be able to pay for what is in service. Rigid node counts push organisations to over-commit early to protect a price.
- Separate acceptance by stage. Acceptance criteria tied to a fully populated cluster force an all-or-nothing sign-off. Stage-level acceptance keeps the programme’s payment and progress in step.
- Make portability explicit. If the interim environment differs from the target, the contract should confirm that workflows, models, indexes, and audit data move without re-licensing. This is the practical test of the concerns raised in Evaluating Vendor Lock-In in Enterprise AI Platforms.
- Model the full cost path, not the hardware invoice. Power, cooling, rack space, network, staffing, and support carry across all stages; see the On-Premise AI Platform Cost and TCO Guide for the wider picture, and GPU Capacity Sourcing for the buy, lease, and colocate trade-offs when lead times are the binding constraint.
Bridging with cloud capacity: a narrow, deliberate option
Teams under schedule pressure often ask whether cloud capacity can cover the gap. The honest answer depends entirely on the data.
For synthetic evaluation data, public reference material, de-identified corpora, or load testing with generated traffic, temporary external capacity is a reasonable bridge and can de-risk Stage 3 sizing. For regulated production data, it usually is not — if residency, confidentiality, or sector rules were the reason for the on-premises decision, a temporary exception reintroduces exactly the exposure the architecture exists to avoid, and it creates a second data path that later has to be decommissioned and evidenced.
Where a bridge is used, treat it as a distinct execution zone with its own classification rules, its own routing policy, and a scheduled end date. The migration mechanics work in both directions; the Cloud to On-Premises AI Migration Playbook covers the data, index, and evidence handover in detail.
Signals worth tracking during the wait
A delayed programme should still report progress in terms a steering committee can act on. Useful indicators during a hardware wait include: source systems with confirmed access, percentage of the corpus with resolved entitlements, size and coverage of the evaluation set, grounded-answer pass rate on that set, workflows with an agreed approval path, and audit fields captured per run.
None of those require the cluster. All of them predict whether Stage 3 will succeed. A programme that can show movement on them during a delay is in a fundamentally different position from one whose only status is a revised delivery date.
How VDF AI fits this sequencing
VDF AI is designed to run inside the customer’s own environment, which means the same platform can be exercised on modest interim capacity and later re-hosted on target hardware without re-architecting the workflow. VDF AI Networks carries the workflow, routing, and execution traces across that move, and VDF AI Agents keeps tool and knowledge access governed with per-execution audit records at both stages. Model routing lets a pilot run on a smaller local model and shift to a larger one when capacity allows, without rewriting the workflow that surrounds it.
The strategic point is simpler than the architecture. Infrastructure schedules will keep moving. A programme whose progress is defined by access, permissions, evaluation, and governance evidence keeps compounding value while it waits; a programme defined by a delivery date does not.
Sources and further reading
- RADCOM Reports Second Quarter 2026 Results
- RADCOM Announces Preliminary Second Quarter Revenue and Updated Full-Year Guidance
- On-Premise AI Implementation Roadmap
- GPU Capacity Sourcing: Buy, Lease, or Colocate
Waiting on hardware and unsure what to build now? Book an on-premises AI readiness session to sequence access, permissions, evaluation, and governance work ahead of the capacity date.